Search Results

452 search results for FORENSIC SCHEDULE ANALYSIS

128R-23
https://web.aacei.org/docs/default-source/rps/128r-23.pdf?sfvrsn=9034abb5_2
, and produce forensic schedule analysis methodologies (Time Impact Analysis, Windows Analysis, etc.) [11, International, Recommended Practice No. 29R-03, Forensic Schedule Analysis, Morgantown, WV: AACE, impact analysis, and delay/acceleration evaluation, and review of periodic schedule updates. 5, and providing schedule progress reports, trending charts, and schedule analysis. 7. Maintaining records, • Planning and scheduling software (schedule development, schedule maintenance, schedule analysis
22437
https://web.aacei.org/docs/default-source/vl-papers/22437.pdf?sfvrsn=89e6d0b5_2
compensable days can be illustrated by a detailed schedule analysis. Even when there is disagreement, by both the Contractor and Owner. (An analysis using the final project schedule with actual dates, construction project when attempts to quantify a delay are presented. Even when schedule analyses that prove, , such as the Baseline Schedule and Schedule of Values, which identify the original Contract Time and Contract Sum, respectively. Contractually, the Schedule of Values is to be used to establish all payments under
ce09-02
https://web.aacei.org/docs/default-source/ce/2009/ce09-02.pdf?sfvrsn=53dfdab5_2
of Building Green President’s Message- Schedule Specifications - Handle with Care, Team FortheBookshelf- Delay Analysis in Construction Contracts The AACE International Bulletin, The A AC E I n t e rnational Journal of Cost Estimation, Cost/Schedule Control, and Project, of Building Green  President’s Message- Schedule Specifications - Handle with Care, and Son Team  For the Bookshelf - Delay Analysis in Construction Contracts  The AACE
22927
https://web.aacei.org/docs/default-source/vl-papers/22927.pdf?sfvrsn=ec2ed4b5_2
provided in the AACE Recommended Practice 29R-03, Forensic Schedule Analysis [3] apply to the analysis, , Forensic Schedule Analysis, Morgantown, WV: AACE International, Latest revision. 4. Section 6.4, review, and work completion tracking. The forensic analysis necessary to demonstrate the responsibility, work, costs in excess of the default subcontractor’s schedule of values) until the costs exceed, schedule. 3 It is this document(s) that is most commonly used to understand what happened on a project
toc_4060-06
https://web.aacei.org/docs/default-source/ppg_toc/toc_4060-06.pdf?sfvrsn=b243dab5_2
Transactions, 1996 98. Schedule Risk Analysis Using Computer Simulation, Joseph J. Orczyk, PE; Dr, Transactions, 1962 119. Utility Rate Case - Schedule Analysis, Anthony J. Werderitsch,PE CCE, . Zimmerman, CCC PSP, AACE Transactions, 2006 56. Schedule Analysis Indices, Gary Rock Spencer, PE; Rose Mary Lewis, PE, AACE Transactions, 2006 57. Claims Analysis Nested in Schedule Updates, 67. Applying Earned Schedule Analysis to EVM data for Estimating Completion Date, Ray W. Stratton
toc_PPG01-E4
https://web.aacei.org/docs/default-source/toc/toc_ppg01-e4.pdf?sfvrsn=e083ddb5_4
Construction, Neil D. Opfer, CCE, AACE Transactions, 1996 98. Schedule Risk Analysis Using Computer, And Experience, Robert B. Vogeler, AACE Transactions, 1962 119.Utility Rate Case - Schedule Analysis, Anthony, Planning, Leah V. Zimmerman, CCC PSP, AACE Transactions, 2006 56. Schedule Analysis Indices, Gary, , Cost Engineering Journal, 2007 67. Applying Earned Schedule Analysis to EVM data for Estimating, A. Bent, AACE Transactions, 1977 3. New Construction Management Emphasis Costs Cost and Schedule
23443
https://web.aacei.org/docs/default-source/vl-papers/23443.pdf?sfvrsn=c0f9acb5_1
compliments and builds upon a forensic delay analysis which is the basis for the calculation, calendar days. The forensic delay analysis performed did not specify the period of delay, , the forensic delay analysis should be used as a tool to aid in the determination of when the delay occurred, to September 1, 2016, a delay of 92 calendar days. The forensic delay analysis showed that the delay, , however, requires more effort as a more detailed forensic delay analysis is needed. As shown
20932
https://web.aacei.org/docs/default-source/vl-papers/20932.pdf?sfvrsn=203deb5_2
the surety's analysis much more difficult as forensic productivity analysis will likely be required, in the cost and schedule analysis discussed later in this article. Site Factors This item can be the cause, in the schedule analysis and cost to complete calculations performed as part of the default analysis, performance for completion of the work. This is accomplished with a schedule analysis. Again, ); generalconditions detail from site analysis and contractor; contractordepreciation schedule
22647
https://web.aacei.org/docs/default-source/vl-papers/22647.pdf?sfvrsn=6404d2b5_10
Recommended Practice No. 29R-03, Forensic Schedule Analysis [2] . SUPPLEMENTAL CALCULATIONS, No. 29R-03 Forensic Schedule Analysis, (Section 2.3 Schedule Updates: Validation, Rectification, Recommended Practice No. 32R-04 DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 – Schedule Planning, DURATIONS TCM Framework: 7.2 – Schedule Planning and Development January 14, 2012 Copyright, guidelines for the project scheduler to determine schedule activity durations and understand
32R-04
https://web.aacei.org/docs/default-source/rps/32r-04.pdf?sfvrsn=edd0dab5_18
Recommended Practice No. 29R-03, Forensic Schedule Analysis [2] . SUPPLEMENTAL CALCULATIONS, No. 29R-03 Forensic Schedule Analysis, (Section 2.3 Schedule Updates: Validation, Rectification, Recommended Practice No. 32R-04 DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 – Schedule Planning, DURATIONS TCM Framework: 7.2 – Schedule Planning and Development January 14, 2012 Copyright, guidelines for the project scheduler to determine schedule activity durations and understand